Blog
Construction Act Review Recommendations
- By: admin
- On: 10/23/2024 16:24:50
- In: October 2024
The OSWCA has recently consulted with the Government of Ontario on upcoming changes related to the Construction Act. Below you will find the OSWCA's recommendations to the Ministry of the Attorney General.
Background:
Ontario's new Construction Act ("the Act") is a critical piece of legislation, reformed in 2017 to create a more equitable business environment for all parties operating in the construction sector. Notably to ensure those procuring improvement for their land, pay for such improvements in a timely fashion, while also ensuring fair and honest dealings and protecting owners of land, general contractors and all subcontractors down the chain. In support of these assurances, the Act enables statutory rights and obligations to be enforced at the least possible expense and in prompt fashion.
At the time of Bill 142's passing, it was recommended that the Act be reviewed within 5 years to evaluate the success of the changes made. Accordingly, in February 2024 the Ontario Attorney General announced they would be embarking on a review process of that statute, prioritizing possible improvements to the Construction Act. The OSWCA is supportive of the amendments creating such rights and obligations and offers the following recommendations to further support the new Regime and the intent of the amendments.
Preventing Penalty for Contractor and Subcontractor Exercise of Rights Under the Act
The OSWCA is supportive of amendments to the Act that will improve project parties' access to and use of adjudication. The use of reprisal clauses, however, directly dissuades contractors and subcontractors from exercising their rights under the Act, including their rights to engage the adjudication process, by providing that, should a person make use of adjudication in accordance with the Act, they may be disqualified or otherwise precluded from participating in future procurement and project opportunities. These clauses intentionally disincentivize parties' exercise of their rights under the Act which is in direct conflict with the foundational principles of the Act and undermines the intent and purpose of fundamental rights and remedies granted under the Act. The OSWCA accordingly recommends the Act be amended to render the use of any such reprisal clauses null and void. Specifically, ensure that no personal shall disqualify or otherwise preclude participation by a contractor in a procurement process, or threaten to do so, because such contractor exercised their rights or otherwise sought remedy under this Act.
Holdback
The changes to lien, holdback and trust provisions that came into force on July 1, 2018 included the introduction of Subsection 22(4) to permit the retaining of holdback in the form of letters of credit and demand-worded holdback repayment bonds instead of in the form of funds. The use of the permitted alternate forms of holdback, however, requires agreement of the parties such that holdback continues to be retained in the form of funds unless the owner agrees to accept an alternate form of holdback. As a result, alternate forms of holdback are not frequently used even where their use would be of great benefit to the contractor and subcontractors by improving project cash flow, particularly on higher value contracts where the quantum of holdback to be retained is significant. The OSWCA accordingly recommends that the Act be amended to allow the contractor to elect to use of other permissible forms of holdback for higher value contracts, such as contracts with a value of $5M or more.
Similar issues arise with respect to the permitted phased and annual release of holdback introduced through the changes to the lien, holdback and trust provisions which came into force on July 1, 2018. Specifically, permitting the release of holdback on a phased or annual basis provides a further opportunity for cash to flow more quickly, while maintaining protections for sub-contractors and lien claims. Unfortunately, due to the permissive wording, this mechanism is seldom utilized, as many contracts do not provide for payment of accrued holdback on a phased or annual basis.
This is particularly troublesome as the phased or annual release of holdback would significantly benefit sub-contractors that have completed their work early in the project and must wait until substantial completion of the project for the release of their holdback. Releasing the holdback on a phased or annual basis would not only help alleviate the carrying cost down the chain, but also provide cost savings to those back up the chain, as contractors and subcontractors know they will be receiving their holdback within months rather than potentially years.In response, the OSWCA recommends adjusting the permissive wording, and rather, mandating the release of holdback on an annual basis for contracts which extend beyond two years.
Improving the Prompt Payment Process
The OSWCA is supportive of the recommendations submitted to the Attorney General by G. Ackerley with respect to "Promptness of Payment". In particular, the lack of obligation for an owner to provide the contractor with notice when an application for payment is rejected or ignored due to being deemed "improper", unnecessarily interrupts and delays the prompt payment process. The OSWCA supports the recommendation to a new definition of "improper invoice" and require and an owner to object to the invoice submitted by a contractor as being "improper" within 3 days of receipt, failing which the invoice submitted by the contractor will be deemed to be considered proper. Without this notice there is no obligation on the owner to acknowledge a proper invoice as a proper invoice when such invoice fails to meet the criteria set out in the contract.
Similarly, timely payment to subcontractors is also undermined where the contractor is under no obligation to timely include subcontractor applications for payment in their proper invoices. As such, the OSWCA supports a recommendation to require contractors to include the full value of the services and materials supplied by all subcontractors in the proper invoice. Subcontractors should also be made aware of when a proper invoice has been issued so that they know when to expect receipt of payment or a notice of non-payment in accordance with the Act.
Please reach out to Krisha Ruchlewicz (krisha.ruchlewicz@oswca.org) if you have any questions relating to the Construction Act.
Categories
- All categories
- April 2025
- March 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
- December 2023
- November 2023
- October 2023
- September 2023
- August 2023
- July 2023
- April 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- November 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- December 2019
- November 2019
- October 2019
- September 2019
- August 2019
- July 2019
- March 2019
- February 2019
- January 2019
- December 2018
- September 2018
- July 2018
- June 2018
- April 2018
- March 2018
- January 2018
- December 2017
- November 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016
- September 2016
- August 2016
- June 2016
- May 2016
- April 2016
- March 2016
- February 2016
- January 2016
- December 2015
- November 2015
- October 2015
- September 2015
- August 2015
- July 2015
- June 2015
- May 2015
- April 2015
- March 2015
- February 2015
- January 2015
- December 2014
- November 2014
- September 2014
- August 2014
- July 2014
- June 2014
- May 2014
- April 2014
- March 2014
- February 2014
- January 2014
- December 2013
- November 2013
- October 2013
- August 2013
- July 2013